ProjectsRosehill’s Production Enhancement Contract (PEC)Rosehill’s role as the contractor under the PEC consists of three components:
Workover OperationsSince 1999 the Contractor has worked over 32 different wells at the North Urtabulak Field producing roughly 1 million barrels of oil, and is currently conducting workovers at 16 wells. Incremental production oil at these wells is allocated as follows:
The New Horizontal Well at the North Urtabulak FieldUnder Phase 1 of the Project Development Plan set out in the PEC, the Contractor is to drill a new horizontal well in the northwest portion of the North Urtabulak Field. The Umid and South Kemachi FieldsUnder the PEC Rosehill and the Uzbek state oil company will jointly rehabilitate
these fields on agreed terms. |